Lost half a day today relocating a mismarked 6-inch water line on a road widening, and I’m trying to keep paving and drainage from sitting idle while we re-sequence. I run a 6:30 a.m. huddle with foremen and adjust P6 on site, but I’m looking for practical plays that protect the critical path without burning float. What’s worked for you — pulling forward minor works, splitting crews, or shifting pour windows?