On a mixed-use infill in Denver, our 14-week utility relocation window is threatening the whole schedule. How are you sequencing civil packages and ROW/encroachment permits so foundations can start by week 20 without rework, and what lead times are you seeing for tap permits and TCP approvals from the city?
Split the civil into an early enabling package for SUE/utility conflicts and ROW/encroachment, then issue a foundations set with oversized sleeves/duct banks across the utility corridors so you can pour by week 20 without tear-outs. > rework, and what lead times are you seeing for tap permits and — we’re seeing 5–7 weeks on taps (Denver Water/Wastewater) and 3–4 weeks on TCP if you bring a 30% MOT to pre-app; ROW/encroachment is the long pole at 6–8 weeks unless you use on‑call traffic control. Is that 14-week relocation in CDOT ROW or just city streets?