And anyone else deal with a late survey showing a 20 mm pier offset after the first girders arrive? I’m the bridge engineer managing both design and construction on a 120 m steel plate girder over I-82, and we ended up moving a field splice and retuning camber with the fabricator to keep a weekend closure — curious where you draw the line between reopening the calc package vs solving it in the field.