Quick question: does anyone have a solid Primavera P6 (v22) template for resource-loaded highway rehab? I’m mapping a 28 km corridor with 6 paving/milling crews and a 300 TPH plant, and I need a clean way to cap daily output by truck fleet and plant capacity while keeping calendars sane — sample resource dictionaries or leveling settings would be huge.
I’d model the cap at the resource level: plant as a nonlabor resource at 300 TPH and each truck fleet as a nonlabor resource sized by trucks×payload÷cycle. > to cap daily output by truck fleet and plant capacity while keeping calendars sane — agree; set paving/milling to Fixed Duration & Units/Time and Resource Dependent, then level by Priority with ‘Limit resource availability to Max Units/Time’ in v22 so daily tonnage can’t exceed either cap; if the plant runs nights, give it its own calendar — what’s your average haul cycle?