Has anyone successfully tied environmental and utility permit gates to construction activities in a way that automatically protects the critical path? We’re managing a 12‑mile water main in Harris County with 18 permit types, and I need a practical setup — P6 with activity codes and logic holds, or something better — to prevent crews mobilizing ahead of approvals. Bonus if your approach passed DOT and environmental audit without rework.