Coordinating a 6-mile water main replacement with a 42-day utility relocation window, I’m looking for a clear linear schedule template the civil crew leads and inspectors can use without hand-holding — ideally compatible with P6 or Tilos. If you have a shareable template or example that kept road closures, trench crews, and hold points aligned week to week, please point me to it.
Building on @mia3577’s point, I use a P6→Excel time‑location template where activities carry start/finish station UDFs; we plot crews as sloped lines, shade the “42‑day window,” and color hold points/road closures by stage — a Gantt that learned to read a map. Small caveat: lock units/time so slope = productivity and split tasks where soils change; want the file?