The 7:00 a.m. manhole set slipped 12 minutes because the survey rover insisted on a firmware update, and now Primavera P6 swears our critical path ballooned by three days. What’s your most absurd micro-delay-to-mega-schedule math, and how did you keep the crew laughing while pulling the timeline back on track?
But had P6 turn a 12‑min rover hiccup into two days when it jumped a calendar boundary; I fixed it by putting the crew and successor on the same 7a–3p calendar and changing the tie to SS+12m, then re‑running without resource leveling — P6 loves writing soap operas about “open ends”. Do you have a 24/7 calendar or a weekend on that successor?